Термофит имеет подтвержденную аттестацию 35 кВ в ПАО Россети №IД-145/25 от 25.07.2025 к Заключению аттестационной комиссии №I3-179/18 от 27.11.2018 (протокол продления №IП-50/24 от 15.04.2024)

Connecting coupling

Installation of a heat-shrinkable cable sleeve on a 10 kV oil cable usually involves the following steps:

  1. Preparation of equipment and materials:

    • Make sure you have all the necessary tools and materials for installation. This may include heat shrink sleeve, heat shrink tubing, electrical tape, screwdrivers, scissors, wire cutters, marking materials, etc.
  2. Preparation of oil cable:

    • Clean and degrease the ends of the oil cable on which the coupling will be installed. Use special cleaners to remove dirt and grease.
  3. Preparing the heat-shrinkable sleeve:

    • Check that the heat shrink sleeve meets the required specifications and dimensions of the oil cable.
    • Install all necessary components on the coupling, such as power contacts, shields and heat shrink tubing.
  4. Installing the coupling on the cable:

    • Open the heat shrink tubing on the coupling and position it on one end of the oil cable.
    • Install the sleeve onto the cable so that the contacts are correctly aligned with the cable conductors.
    • Make sure that the heat shrink tubing completely covers the connection between the sleeve and the cable.
  5. Heat shrink:

    • Use a heat shrink oven or heat gun to heat the shrink tubing. Ensure that the heat shrink temperature and time are in accordance with the coupling manufacturer's specifications.
    • When heat shrink tubing is heated, it shrinks and forms a tight connection between the sleeve and the cable, providing electrical insulation.
  6. Connection protection:

    • Secure the heat shrink sleeve and cable with electrical tape to provide additional protection and prevent movement or damage to the connection.
  7. Inspection and marking:

    • Once installation is complete, check the connection to ensure it is properly installed and insulated.
    • Mark the coupling and cable with appropriate markers or labels for identification and ease of maintenance.

When installing a cable heat-shrinkable sleeve on a 10 kV oil cable, it is important to follow the instructions of the sleeve manufacturer and observe electrical safety, especially when working with high-voltage electrical conductors. If you do not have experience or knowledge in this area, it is recommended that you have a professional or qualified person perform the installation.